Project Introduction

Contract Overview

 
 
Site formation
 
 
Construction of the relevant retaining structures
 
 
Demolition of existing noise barriers along Ma On Shan Road and re-provision of temporary noise barriers
 
 
Construction of a temporary vehicular bridge
 
 
Temporary diversion of a section of the existing footpath and cycle track
 
 
Construction of a section of access tunnel
 
 
Construction of the access road adjoining A Kung Kok Shan Road and the proposed ventilation shaft
 
 
Construction of Community Liaison Centre

Layout Plan



1 2 3 4 5 6 7 8

Description

Contract No DC/2018/05
Contract Title Relocation of Sha Tin Sewage Treatment Works to Caverns – Site Preparation and Access Tunnel Construction
Consultant AECOM Asia Company Limited
Contractor China State Joint Venture
Date of Commencement 28 February 2019
Anticipated Date of Completion End 2022
Contract Sum HK$811,405,000.00